Bellefonte Units 3 & 4

Licensing Status:      Review Suspended 9/29/2010

Site:                             TVA's Bellefonte site near Scottsboro in Jackson County, Alabama

Reactor:                      Westinghouse Advanced Passive 1000 (AP1000)
                                     Pressurized Water Reactors (PWRs)

Projected Online:     Unit 3 - 2017

                                    Unit 4 – 2019

In the News:                Bellefonte Units 3 & 4

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

10/30/07 - A

Acceptance Review

Acceptance Review Start

11/07/07 - A

Docketing Decision Letter Issued/Acceptance Review Complete

01/18/08 - A

Review Schedule Established/Schedule Letter Issued to Applicant

02/15/08 - A

Safety Review

Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant

01/16/09 - A

Phase 2 - SER with Open Items issued (without hydrology and Chapter 6)

02/10 - A

Phase 3 - ACRS Review of SER with Open Items Complete (without hydrology)

04/10 - A

Phase 4 - Advanced SER with no Open Items Issued

09/10 - T*

Phase 5 - ACRS Review of SER with no Open Items Complete

01/11 - T*

Phase 6 - Final SER Issued

03/11 - T*

Environmental Review

Phase 1 - Environmental impact statement (EIS) summary report issued

08/15/08 - A

Phase 2 - Draft EIS issued to EPA

03/06/09 - T**

Phase 3 - Response to public comments on draft EIS issued

08/10/09 - T**

Phase 4 - Final EIS issued to EPA

01/10 - T**

Hearing

Commission or ASLB hold mandatory hearing

 

License

Commission decision on issuance of COL application

 

* Dates for Safety review schedule do not reflect the change in the schedule because of issues with the hydrology review (see NRC letter dated October 29, 2008).

** Dates for Environmental review do not reflect the change in the schedule because of the NRC’s decision to not issue the draft EIS until TVA makes a decision on whether or not it will complete Bellefonte 1 and 2 (see NRC letter dated July 21, 2009).

Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/bellefonte.html