Turkey Point Units 6 & 7

Licensing Status:      Schedule Under Review

Site:                       Existing Site Turkey Point

Reactor:                  Westinghouse Advanced Passive 1000 (AP1000)
                              Pressurized Water Reactors (PWRs)

Projected Online:      2022 - 2023

In the News:            Turkey Point Units 6 & 7

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

06/30/09 - A

Acceptance Review

Acceptance Review Start

06/30/09 - A

Docketing Decision Letter Issued/Acceptance Review Complete

09/04/09 - A

Review Schedule Established/Schedule Letter Issued to Applicant

05/28/10 - A

Safety Review

Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs

03/12 - T

Phase B - Advance Final safety evaluation report (SER) without Open Items

01/13 - T

Phase C - ACRS Review of Advance Final SER

07/13 - T

Phase D - Final SER

11/13 - T

Environmental Review

Phase 1 - Environmental impact statement (EIS) scoping summary report issued

12/10 - A

Phase 2 - Draft EIS issued to EPA

02/13 - T

Phase 3 - Final EIS issued to EPA

02/14 - T

Hearing

Commission or ASLB hold mandatory hearing

06/14 - T 

License

Commission decision on issuance of COL application

 

Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html