Virgil C Summer Units 2 & 3

Licensing Status:      Scheduled

Site:                       Existing Site Virgil C Summer

Reactor:                  Westinghouse Advanced Passive 1000 (AP1000)
                              Pressurized Water Reactors (PWRs)

Projected Online:      Unit 3 - 2016
                             Unit 4 – 2019

In the News:             Virgil C Summer Units 2 & 3

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

03/27/08 - A

Acceptance Review

Acceptance Review Start

06/02/08 - A

Docketing Decision Letter Issued/Acceptance Review Complete

07/31/08 - A

Review Schedule Established/Schedule Letter Issued to Applicant

09/26/08 - A

Safety Review

Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
(Formerly Phase 1 and 2)

09/10/09 - A

Phase B - Advanced Final safety evaluation report (SER) without Open Items
(Formerly Phase 4)

12/10/10 – A

Phase C - ACRS Review of Advanced Final SER
(Formerly Phase 5)

03/26/11 - A

Phase D - Final SER
(Formerly Phase 6)

08/17/11 - A

Environmental Review

Phase 1 - Scoping

07/15/09 - A

Phase 2 - Draft Environmental Impact Statement (DEIS)

04/16/10 - A

Phase 3 - Response to Public Comments on DEIS completed

08/10 - A

Phase 4 - Final Environmental Impact Statement

04/11 - A

Hearing

Commission or ASLB hold mandatory hearing

01/12 - A

License

Commission decision on issuance of COL application

03/20 - A


Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/summer.html