Reactor: PWR
Output: 300 MWe
Location: Kundian, Punjab, Pakistan
- 2004 - Contract signed for unit 2
- April 2005 - Ceremony was held by both parties of China and Pakistan
- December 2005 - First concrete poured at unit 2
- 2007 - Success of the dome placement of C-2 Project
- April 2009 - Contract signed for units 3 and 4
- April 2011 - Unit 2 begins operation