Calvert Cliffs Unit 3

Licensing Status:     Scheduled

Site:                      Existing Site Calvert Cliffs

Reactor:                 AREVA U.S. Evolutionary Power Reactor (U.S. EPR)

Projected Online:      Unit 3 – 2016 - 2018

In the News:            Calvert Cliffs Unit 3

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

07/13/07 &
03/14/08 - A

Acceptance Review

Acceptance Review Start

07/16/07 &
04/01/08 - A

Docketing Decision Letter Issued/Acceptance Review Complete

01/25/08 &
06/03/08 - A

Review Schedule Established/Schedule Letter Issued to Applicant

07/14/09 - A

Safety Review

Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant

04/12/10 - A

Phase 2 - SER with Open Items issued

04/27/11 - T

Phase 3A - ACRS Review of SER with Open Items Complete (early chapters)

02/19/10 - A

Phase 3B - ACRS Review of SER with Open Items Complete (late chapters)

07/11 - T

Phase 4 - Advanced SER with no Open Items Issued

01/12 - T

Phase 5 - ACRS Review of SER with no Open Items Complete

05/12 - T

Phase 6 - Final SER Issued

07/12 - T

Environmental Review

Phase 1 - Environmental impact statement (EIS) summary report issued

10/06/08 - A

Phase 2 - Draft EIS issued to EPA

04/16/10 - A

Phase 3 - Response to public comments on draft EIS resolved

08/27/10 - A

Phase 4 - Final EIS issued to EPA

05/13/11 - T

Hearing

Commission or ASLB hold mandatory hearing

 

License

Commission decision on issuance of COL application

 

Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/calvert-cliffs.html