Fermi Unit 3

Licensing Status:     Scheduled

Site:                      Existing Site - Fermi

Reactor:                 Economic Simplified Boiling Water Reactor (ESBWR)

Projected Online:     2020

In the News:           Fermi Unit 3

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

09/18/08 - A

Acceptance Review

Acceptance Review Start

09/18/08 - A

Docketing Decision Letter Issued/Acceptance Review Complete

11/25/08 - A

Review Schedule Established/Schedule Letter Issued to Applicant

06/30/09 - A

Safety Review

Phase 1 - Requests for Additional Information (RAIs) and Supplemental RAIs

08/20/10 - A

Phase 2 - Advanced Final Safety Evaluation Report (SER) without Open Items

09/12 - T

Phase 3 - ACRS Review of SER without Open Items

02/13 - T

Phase 4 - Final SER

05/13 - T

Environmental Review

Phase 1 - Environmental Impact Statement (EIS) Scoping Summary Report Issued

07/02/09 - A

Phase 2 - EPA Issues Federal Register Notice of Filing for Draft EIS/Draft EIS Complete

10/11 - T

Phase 3 - Federal Register Notice of Availability of the FEIS Published/Final EIS Complete

11/12 - T

Hearing

Commission or ASLB hold mandatory hearing

 

License

Commission decision on issuance of COL application


 

Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/fermi.html