Unit 2 Barakah Hot Functional Testing Is Done

The Emirates Nuclear Energy Corporation (ENEC) said Monday that hot functional testing (HFT) for Unit 2 of the Barakah Nuclear Energy Plant had been completed.

Barakah NPP"This significant pre-operational testing process incorporated all lessons learned from the same test on Unit 1 in order to achieve the highest international standards of quality, safety and efficiency," ENEC said in a statement.

ENEC worked the plant's contractor/designer, the Korea Electric Power Corporation (KEPCO), the Joint Venture partner and Prime Contractor for the Barakah project. The work is being done under the regulatory guidelines of the Federal Authority for Nuclear Regulation (FANR), the UAE’s independent nuclear regulatory body.

HFT took place over a number of weeks and consisted of almost 200 individual and integrated tests performed on major systems to check their performance under normal operational conditions, without the presence of nuclear fuel in the reactor.

The test includes the first time that most of the reactor’s systems experience the operational temperature of nearly 300 degrees Celsius and operational pressure of more than 150 kilograms per square centimeter, which is the equivalent of 1,500 meters below water. It is also the first time that the turbine is spun at its maximum speed of 1,500 rates per minute (RPM), demonstrating its readiness to operate once the reactor starts up for normal operations.

During the HFT, components were checked for thermal expansion, vibration and wear. "The results demonstrate that all systems perform in accordance with the highest quality and safety standards under normal operating conditions," ENEC said. "Most notably, the pressurizer safety valve test, pre-core reactor coolant system flow measurement test and main turbine system test were performed, proving that major components and systems work as designed and meet all requirements for normal operation."

"By incorporating the lessons learned from the same tests on Unit 1, we continue to establish Barakah as the benchmark for new nuclear construction projects worldwide,” said Eng. Mohamed Al Hammadi, Chief Executive Officer of ENEC. “Keeping construction progress approximately one year apart for each of the Units at Barakah makes it possible for us to implement all lessons learned from one Unit to the subsequent ones, in line with international best practices in the management of megaprojects”.

Along with testing the performance of a wide range of components, the HFT provided plant operators from Nawah Energy Company (Nawah), the Joint Venture subsidiary in charge of operations, the opportunity to control pressure and temperature safety-related equipment, start and place the turbine in service, and complete various other operating procedures. This gave operators a unique ability to identify any issues with procedures or the equipment and take corrective actions to ensure that once it is started up, the plant will operate safely and sustainably for the coming decades.

Construction of Unit 2 of the Barakah Nuclear Energy Plant began in April 2013, one year after Unit 1. All four units at the Barakah Nuclear Energy Plant are progressing safely and steadily, with Unit 1 construction completed and turned over to Nawah for preparation to operate, pending regulatory approval.

As of end of June 2018, the construction progress rate of Unit 2 of the Barakah Plant 93 percent and overall construction progress rate for the four Units is now more than 89 percent, ENEC said.

Anonymous comments will be moderated. Join for free and post now!