Comanche Peak Units 3 & 4
Licensing Status: Scheduled Dependent on DC Review
Site: Existing Site Comanche Peak
Reactor: United States Advanced Pressurized Water Reactor (US-APWR)
Projected Online: May 2018
In the News: Comanche Peak
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
09/19/08 - A
Acceptance Review
Acceptance Review Start
09/22/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
12/02/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
03/16/09 - A
Safety Review
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant
10/09/09 - A
Phase 2 - SER with Open Items issued
03/12-T
Phase 3 - ACRS Review of SER with Open Items Complete
07/12-T
Phase 4 - Advanced SER with no Open Items Issued
12/12-T
Phase 5 - ACRS Review of SER with no Open Items Complete
03/13-T
Phase 6 - Final SER Issued
06/13-T
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
07/02/09 - A
Phase 2 - Draft EIS Complete
08/06/10 - A
Phase 3 - Public Comment Period for DEIS ends
10/27/10 - A
Phase 4 - Final EIS issued
05/13/11 - A
Hearing
Commission or ASLB hold mandatory hearing
12/14 - T
License
Commission decision on issuance of COL application
On December 7, 2011, the NRC staff revised the review schedule for the Comanche Peak Nuclear Power Plant, Units 3 and 4 Combined License Application.
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/comanche-peak.html