Levy County Units 1 & 2
Licensing Status: Scheduled
Site: PEF's site in Levy County, Florida
Reactor: Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs)
Projected Online: Unit 1 - 2021 Unit 2 – 2023
In the News: Levy County Units 1 & 2
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
07/30/08 - A
Acceptance Review
Acceptance Review Start
08/04/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
10/06/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
02/18/09 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs(Formerly Phase 1)
03/29/10 - A
Phase B - Advanced Final safety evaluation report (SER) without Open Items(Formerly Phase 2)
09/11 - T
Phase C - ACRS Review of Advanced Final SER(Formerly Phase 3)
01/12 - T
Phase D - Final SER(Formerly Phase 4)
04/12 - T
Environmental Review
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
05/28/09 - A
Phase 2 - Draft EIS issued to EPA
08/06/10 - A
Phase 3 - Responses to public comments on draft EIS completed**
11/11 - T
Phase 4 - Final EIS issued to EPA
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of COL application
**NRC staff responses to public comments on the Draft EIS are considered to be in draft form and subject to change. The final version of the document will be publicly released as an appendix to the Final EIS