Turkey Point Units 6 & 7
Licensing Status: Schedule Under Review
Site: Existing Site Turkey Point
Reactor: Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs)
Projected Online: 2022 - 2023
In the News: Turkey Point Units 6 & 7
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
06/30/09 - A
Acceptance Review
Acceptance Review Start
Docketing Decision Letter Issued/Acceptance Review Complete
09/04/09 - A
Review Schedule Established/Schedule Letter Issued to Applicant
05/28/10 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
03/12 - T
Phase B - Advance Final safety evaluation report (SER) without Open Items
01/13 - T
Phase C - ACRS Review of Advance Final SER
07/13 - T
Phase D - Final SER
11/13 - T
Environmental Review
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
12/10 - A
Phase 2 - Draft EIS issued to EPA
02/13 - T
Phase 3 - Final EIS issued to EPA
02/14 - T
Hearing
Commission or ASLB hold mandatory hearing
06/14 - T
License
Commission decision on issuance of COL application
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html