Nuclear Street - Nuclear Power Plant News, Jobs, and Careers

  • Site
  • User
  • Site
  • Search Nuclear Street
  • User
  • Home
  • Buyers Guide
  • Marketplace
  • Jobs
  • Forums
  • Nuclear News
  • Support
  • More
  • Cancel
  • -New Nuclear Power Plants Worldwide
    • +Argentina
    • +Bulgaria
    • +China
    • +Finland
    • +France
    • +India
    • +Iran
    • +Japan
    • +Pakistan
    • +Russia
    • +Slovak Republic
    • +South Korea
    • +Taiwan
    • +Ukraine
    • -USA
      • Bell Bend Unit 1
      • Bellefonte Units 3 & 4
      • Blue Castle Project
      • Callaway Unit 2
      • Calvert Cliffs Unit 3
      • Comanche Peak
      • Fermi Unit 3
      • Grand Gulf Unit 3
      • Harris Units 2 & 3
      • Levy County Units 1 & 2
      • Nine Mile Point Unit 3
      • North Anna Unit 3
      • PSEG Site ESP
      • River Bend Unit 3
      • South Texas Project Units 3 & 4
      • Turkey Point Units 6 & 7
      • TVA Clinch River
      • Victoria County Units 1 & 2
      • Virgil C Summer Units 2 & 3
      • Vogtle Units 3 & 4
      • William Lee Nuclear Station Units 1 & 2
  • +Fukushima - Nuclear Power Plant
  • +Nuclear Power Plants Worldwide
  • +Nuclear Power Videos
  • +Reactors
  • +Reference
  • What to read about nuclear energy?
Related Content
Recommended Content

Turkey Point Units 6 & 7

Turkey Point Units 6 & 7

Licensing Status:      Schedule Under Review

Site:                       Existing Site Turkey Point

Reactor:                  Westinghouse Advanced Passive 1000 (AP1000)
                              Pressurized Water Reactors (PWRs)

Projected Online:      2022 - 2023

In the News:            Turkey Point Units 6 & 7

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

06/30/09 - A

Acceptance Review

Acceptance Review Start

06/30/09 - A

Docketing Decision Letter Issued/Acceptance Review Complete

09/04/09 - A

Review Schedule Established/Schedule Letter Issued to Applicant

05/28/10 - A

Safety Review

Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs

03/12 - T

Phase B - Advance Final safety evaluation report (SER) without Open Items

01/13 - T

Phase C - ACRS Review of Advance Final SER

07/13 - T

Phase D - Final SER

11/13 - T

Environmental Review

Phase 1 - Environmental impact statement (EIS) scoping summary report issued

12/10 - A

Phase 2 - Draft EIS issued to EPA

02/13 - T

Phase 3 - Final EIS issued to EPA

02/14 - T

Hearing

Commission or ASLB hold mandatory hearing

06/14 - T 

License

Commission decision on issuance of COL application

 

Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/turkey-point.html

  • Turkey Point
  • New Nuclear Plant
  • USA
  • Share
  • History
  • More
  • Cancel

Advertise With Us | Terms and Conditions | Privacy | Copyright | Contact Us

Other Energy Markets: Renewable Energy Street (Coming Soon!)| Oil and Gas Street (Coming Soon!)
Copyright (c) 2023 NuclearStreet.com - A Media X Group Digital Property