Victoria County Units 1 & 2
Licensing Status: Scheduled
Site: TBD
Reactor: General Electric Advanced Boiling Water Reactor (ABWR)
Projected Online: TBD
In the News: Victoria County Units 1 & 2
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
03/25/10 - A
Acceptance Review
Acceptance Review Start
04/01/10 - A
Docketing Decision Letter Issued/Acceptance Review Complete
06/08/10 - A
Review Schedule Established/Schedule Letter Issued to Applicant
08/10 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs issued
10/11 - T
Phase B - Advanced safety evaluation report (SER) with no Open Items developed
08/12 - T
Phase C - ACRS meeting on Advanced SER
12/12 - T
Phase D - Final SER issued
04/13 - T
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
07/11 - T
Phase 2 - Draft EIS issued to EPA
Phase 3 - Final EIS issued to EPA
08/13 - T
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of Early Site Permit
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/esp/victoria.html