Nuclear Street - Nuclear Power Plant News, Jobs, and Careers

  • Site
  • User
  • Site
  • Search Nuclear Street
  • User
  • Home
  • Buyers Guide
  • Marketplace
  • Jobs
  • Forums
  • Nuclear News
  • Support
  • More
  • Cancel
  • -New Nuclear Power Plants Worldwide
    • +Argentina
    • +Bulgaria
    • +China
    • +Finland
    • +France
    • +India
    • +Iran
    • +Japan
    • +Pakistan
    • +Russia
    • +Slovak Republic
    • +South Korea
    • +Taiwan
    • +Ukraine
    • -USA
      • Bell Bend Unit 1
      • Bellefonte Units 3 & 4
      • Blue Castle Project
      • Callaway Unit 2
      • Calvert Cliffs Unit 3
      • Comanche Peak
      • Fermi Unit 3
      • Grand Gulf Unit 3
      • Harris Units 2 & 3
      • Levy County Units 1 & 2
      • Nine Mile Point Unit 3
      • North Anna Unit 3
      • PSEG Site ESP
      • River Bend Unit 3
      • South Texas Project Units 3 & 4
      • Turkey Point Units 6 & 7
      • TVA Clinch River
      • Victoria County Units 1 & 2
      • Virgil C Summer Units 2 & 3
      • Vogtle Units 3 & 4
      • William Lee Nuclear Station Units 1 & 2
  • +Fukushima - Nuclear Power Plant
  • +Nuclear Power Plants Worldwide
  • +Nuclear Power Videos
  • +Reactors
  • +Reference
  • What to read about nuclear energy?
Related Content
Recommended Content

Virgil C Summer Units 2 & 3

Virgil C Summer Units 2 & 3

Licensing Status:      Scheduled

Site:                       Existing Site Virgil C Summer

Reactor:                  Westinghouse Advanced Passive 1000 (AP1000)
                              Pressurized Water Reactors (PWRs)

Projected Online:      Unit 3 - 2016
                             Unit 4 – 2019

In the News:             Virgil C Summer Units 2 & 3

NRC Application Review Schedule

Key Milestones

Completion Date
Actual - A
Target - T

Application Tendered

03/27/08 - A

Acceptance Review

Acceptance Review Start

06/02/08 - A

Docketing Decision Letter Issued/Acceptance Review Complete

07/31/08 - A

Review Schedule Established/Schedule Letter Issued to Applicant

09/26/08 - A

Safety Review

Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
(Formerly Phase 1 and 2)

09/10/09 - A

Phase B - Advanced Final safety evaluation report (SER) without Open Items
(Formerly Phase 4)

12/10/10 – A

Phase C - ACRS Review of Advanced Final SER
(Formerly Phase 5)

03/26/11 - A

Phase D - Final SER
(Formerly Phase 6)

08/17/11 - A

Environmental Review

Phase 1 - Scoping

07/15/09 - A

Phase 2 - Draft Environmental Impact Statement (DEIS)

04/16/10 - A

Phase 3 - Response to Public Comments on DEIS completed

08/10 - A

Phase 4 - Final Environmental Impact Statement

04/11 - A

Hearing

Commission or ASLB hold mandatory hearing

01/12 - A

License

Commission decision on issuance of COL application

03/20 - A


Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/summer.html

  • summer
  • Virgil C Summer
  • VC Summer
  • New Nuclear Plant
  • USA
  • Share
  • History
  • More
  • Cancel

Advertise With Us | Terms and Conditions | Privacy | Copyright | Contact Us

Other Energy Markets: Renewable Energy Street (Coming Soon!)| Oil and Gas Street (Coming Soon!)
Copyright (c) 2023 NuclearStreet.com - A Media X Group Digital Property