You are currently reviewing an older revision of this page.
William Lee Nuclear Station Units 1 & 2
Licensing Status: Scheduled
Site: Duke's Lee site near Charlotte in Cherokee County, South Carolina
Reactor: Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs)
Projected Online: Unit 3 - 2016 Unit 4 – 2017
In the News: William Lee Nuclear Station Units 1 & 2
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
12/13/07 - A
Acceptance Review
Acceptance Review Start
01/02/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
02/25/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
04/02/08 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) Issued to Applicant(Formerly Phases 1, 2, and 3)
05/20/10 - A
Phase B - Advanced Final Safety Evaluation Report (SER) without Open Items(Formerly Phase 4)
02/12 - T*
Phase C - ACRS Review of Advanced Final SER(Formerly Phase 5)
05/12 - T*
Phase D - Final SER(Formerly Phase 6)
08/12 - T*
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
09/11/08 - A
Phase 2 - Draft EIS issued to EPA
07/2011
Phase 3 - Response to public comments on draft EIS completed
02/2012
Phase 4 - Final EIS issued to EPA
08/2012
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of COL application
*Dates do not yet reflect the recent changes to the Westinghouse and Vogtle (reference COL) review schedules.
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/lee.html