Calvert Cliffs Unit 3
Licensing Status: Scheduled
Site: Existing Site Calvert Cliffs
Reactor: AREVA U.S. Evolutionary Power Reactor (U.S. EPR)
Projected Online: Unit 3 – 2016 - 2018
In the News: Calvert Cliffs Unit 3
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
07/13/07 &03/14/08 - A
Acceptance Review
Acceptance Review Start
07/16/07 &04/01/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
01/25/08 &06/03/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
07/14/09 - A
Safety Review
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant
04/12/10 - A
Phase 2 - SER with Open Items issued
04/27/11 - T
Phase 3A - ACRS Review of SER with Open Items Complete (early chapters)
02/19/10 - A
Phase 3B - ACRS Review of SER with Open Items Complete (late chapters)
07/11 - T
Phase 4 - Advanced SER with no Open Items Issued
01/12 - T
Phase 5 - ACRS Review of SER with no Open Items Complete
05/12 - T
Phase 6 - Final SER Issued
07/12 - T
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
10/06/08 - A
Phase 2 - Draft EIS issued to EPA
04/16/10 - A
Phase 3 - Response to public comments on draft EIS resolved
08/27/10 - A
Phase 4 - Final EIS issued to EPA
05/13/11 - T
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of COL application
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/calvert-cliffs.html