Fermi Unit 3
Licensing Status: Scheduled
Site: Existing Site Fermi Unit 3
Reactor: Economic Simplified Boiling Water Reactor (ESBWR)
Projected Online: 2017 – 2018
In the News: Fermi Unit 3
NRC Application Review Schedule
Key Milestones
Completion Date Actual - A Target - T
Application Tendered
09/18/08 - A
Acceptance Review
Acceptance Review Start
Docketing Decision Letter Issued/Acceptance Review Complete
11/25/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
06/30/09 - A
Safety Review
Phase 1 - Requests for Additional Information (RAIs) and Supplemental RAIs
08/20/10 - A
Phase 2 - Advanced Final Safety Evaluation Report (SER) without Open Items
11/11 - T
Phase 3 - ACRS Review of SER without Open Items
04/12 - T
Phase 4 - Final SER
09/12 - T
Environmental Review
Phase 1 - Environmental Impact Statement (EIS) Scoping Summary Report Issued
07/02/09 - A
Phase 2 - EPA Issues Federal Register Notice of Filing for Draft EIS/Draft EIS Complete
10/11 - T
Phase 3 - Federal Register Notice of Availability of the FEIS Published/Final EIS Complete
11/12 - T
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of COL application
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/fermi.html