Licensing Status: Issued
Site: Existing Site North Anna
Reactor: Advanced Pressurized Water Reactor (US-APWR)
Projected Online: Unit 3 - TBD
In the News: North Anna Unit 3
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
11/27/07 - A
Acceptance Review
Acceptance Review Start
12/03/07 - A
Docketing Decision Letter Issued/Acceptance Review Complete
01/28/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
03/02/11 - A
Safety Review
Phase A - Preliminary Safety Evaluation Report (SER) and Requests for Additional Information Issued
03/12 - T
Phase B - Advanced SER with no Open Items (OIs) Issued
12/12 - T
Phase C - Advisory Committee on Reactor Safeguards Review of SER with no Open Items Complete
05/13 - T
Phase D - Final SER Issued
07/13 - T
Environmental Review
Draft Supplemental Environmental Impact Statement (EIS) issued
Final Supplemental EIS issued
10/12 - T
Hearing
Commission hold mandatory hearing
11/13 - T
License
Commission decision on issuance of COL application
Additional information can be found at http://www.nrc.gov/reactors/new-reactors/col/north-anna.html