Key Milestones
Completion DateActual - ATarget - T
Application Tendered
05/25/10 - A
Acceptance Review
Acceptance Review Start
06/03/10 - A
Docketing Decision Letter Issued/Acceptance Review Complete
08/04/10 - A
Review Schedule Established/Schedule Letter Issued to Applicant
11/29/10 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs issued
01/2012 - T
Phase B - Advanced Safety Evaluation (SE) with no Open Items developed
11/2012 - T
Phase C - ACRS meeting on Advanced SE
03/2013 - T
Phase D - Final Safety Evaluation Report (SER) issued
07/2013 - T
Environmental Review
Phase 1 - Scoping Period Ends
12/2010 - A
Phase 2 - Draft Environmental Impact Statement (EIS) issued to EPA
03/2012 - T
Phase 3 - Public comment period for Draft EIS ends
07/2012 - T
Phase 4 - Final EIS issued to EPA
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of Early Site Permit