Harris Units 2 & 3
Licensing Status: Scheduled
Site: Existing Site Shearon Harris
Reactor: Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs)
Projected Online: 2019 - 2020
In the News: Shearon Harris Units 2 & 3
NRC Application Review Schedule
Key Milestones
Completion DateActual - ATarget - T
Application Tendered
02/19/08 - A
Acceptance Review
Acceptance Review Start
02/20/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
04/17/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
05/16/08 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) Issued to Applicant(Formerly Phases 1, 2, and 3)
04/20/10 - A
Phase B - Advanced Final Safety Evaluation Report (SER) without Open Items(Formerly Phase 4)
04/13 - T*
Phase C - ACRS Review of Advanced Final SER(Formerly Phase 5)
07/13 - T*
Phase D - Final SER(Formerly Phase 6)
09/13 - T*
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
11/18/08 - A
Phase 2 - Draft EIS issued to EPA
01/2013
Phase 3 - Response to public comments on draft EIS completed
06/2013
Phase 4 - Final EIS issued to EPA
01/2014
Hearing
Commission or ASLB hold mandatory hearing
License
Commission decision on issuance of COL application
*Dates do not yet reflect the recent changes to the Westinghouse and Vogtle (reference COL) review schedules.